13 Aug 2026
Passengers are being urged to plan ahead next month as Network Rail carries out essential engineering work to improve the reliability and resilience of the railway across North Wales and the Borders.
The work will take place between Sunday 16 August and Sunday 30 August, with the railway reopening on Monday 31 August.
A key focus of the work is tackling two locations that have been repeatedly affected by flooding during periods of heavy rainfall. Near Gobowen, engineers will replace an ageing syphon and install the first automated trash screen on the Wales and Borders route. Powered by water and solar energy, the system automatically removes branches, weeds and litter before they can block the drainage system, delivering a more reliable railway for passengers.
Additional work includes:
- Babbinswood: More than a kilometre of drainage pipe renewal to improve the area's resilience to extreme weather.
- Hawarden Swing Bridge: Structural repairs, sections of track replaced, waterproofing, and completing brickwork repairs to improve the long-term conditions and keep trains running reliably.
- Route improvements: Track renewals, level crossing upgrades, rail stressing and signalling work between Shotwick, Dee Marsh Junction, Weston Rhyn, Ruabon and Burton.
By completing multiple projects during the same closure, Network Rail is minimising the need for future planned disruption while delivering lasting improvements across the route.
Nick Millington, Route Director for Network Rail Wales and Borders, said: "This is a significant investment in the railway across North Wales and the Borders that will deliver long-term benefits for passengers and freight customers.
"Much of the work is focused on improving drainage and replacing ageing infrastructure at locations that have experienced repeated flooding. These upgrades will make the railway more resilient to extreme weather, helping to reduce delays and improve reliability for years to come.
"We've also planned a wide range of additional improvements during the closure to make the very best use of the time available and reduce the need for future disruption.
"The programme has been scheduled to begin after the 2026 FA Community Shield in Cardiff, allowing supporters travelling to and from the match to do so before the railway closes. We'd like to thank passengers for their patience and encourage everyone travelling during the closure to plan ahead and check before they travel."
Travel information
Engineering work means all lines between Bidston and Wrexham General will be closed from Sunday 16 August until Sunday 30 August, with some lines between Wrexham General and Shrewsbury also closed during this period.
Passengers should allow extra time for their journeys and check before travelling.
Bidston – Wrexham General/Central | Sunday 16 – Sunday 30 August
- Buses will replace trains between Bidston and Wrexham General/Central, running approximately every 45 minutes from Monday to Saturday, and hourly on Sunday.
- Replacement buses will also serve Birkenhead North for connections with Merseyrail services to Liverpool.
Wrexham General – Shrewsbury | Monday 17 – Sunday 30 August
- Buses will replace trains between Shrewsbury and Wrexham General, running approximately every hour from Monday to Saturday, and up to two-hourly on Sunday. Some services will be extended to Chester.
- Trains between North Wales, Shrewsbury, Birmingham International and Cardiff Central will be diverted via Crewe, with revised timetables and longer journey times.
Some public footpath crossings will also be temporarily closed with signed diversion routes in place. At Gobowen level crossing, barriers may remain down for longer than usual while engineering trains access the work sites.
Passengers are encouraged to check before travelling via National Rail Enquiries or with their train operator before setting off.
Notes to editors
- To support Wrexham fans travelling to Cardiff for their opening game of the season on the evening on Monday 17th August. Transport for Wales is providing a return journey to Wrexham via Shrewsbury (arrives 00:42), Crewe and Chester, leaving Cardiff Central at 22:36.
- A bus service will be provided at Shrewsbury (departing 00:55) for intermediate stations to Gobowen, Chirk and Ruabon.
- Near Gobowen, engineers will replace an ageing syphon – a specialist structure that carries water beneath the railway - alongside renewing drainage pipes and installing the first automated trash screen on the Wales and Borders route. Powered by water and solar energy, the innovative system will automatically remove branches, weeds and litter before they can block the drainage system, helping improve efficiency as Network Rail continues to adopt new technologies that deliver a more reliable railway for passengers.
- At Babbinswood, more than a kilometre of drainage pipe will also be renewed to improve the area's resilience to extreme weather. The improvements will:
- Reduce the risk of flooding and delays during heavy rainfall.
- Improve reliability for passengers and freight services.
- Enhance safety by removing the need for staff to manually clear debris in hazardous conditions.
- Reduce ongoing maintenance requirements.
- Support a more sustainable railway through the use of water and solar-powered technology.
- Engineers will carry out significant repairs to Hawarden Swing Bridge, replacing sections of track, strengthening the structure, improving drainage and waterproofing, and completing brickwork repairs. The work will improve the long-term condition of the bridge, reduce future maintenance requirements and help keep trains running reliably.
- While rail replacement services are in place, passengers must hold a valid ticket before boarding.
- Pay as you go remains available between Bidston and Wrexham Central. Passengers should tap in and out using station platform validators as usual and can correct missed taps via the TfW app or website the following day. To support customers during the disruption, the monthly missed tap correction limit will be temporarily increased from 6 to 14 in August.